Purpose and distinction
The production agreement governs the long-term manufacture of a food by a manufacturer for a principal. Unlike classic contract manufacturing, which often involves individual orders processed to the principal’s recipe, the production agreement focuses on the long-term commitment of capacity. The manufacturer frequently invests in equipment, staff or approvals, and in return the principal commits to quantities and a term.
Typical arrangements are the manufacture of sausage and meat products for a branded goods company, the processing of milk into cheese for a retail chain, the cutting and packing of poultry on behalf of a customer, or the production of ready meals for chain restaurants. The production agreement is particularly common for food of animal origin, because manufacture requires an approval under Article 4 of Regulation (EC) No 853/2004 that not every brand owner holds itself.
Legally, the production agreement is a continuing obligation with elements of sale and of a contract for work. Sales law generally applies to the individual deliveries via Section 650 of the German Civil Code (BGB). There are no statutory models for investments, capacity reservation and exclusivity, so the contract has to regulate them itself.
Checklist of the key clauses
- Products and specifications: recipe, raw material quality, process, packaging, labelling, change procedure.
- Capacity and quantities: reserved capacity, annual quantities, forecast, tolerances, consequences of shortfalls.
- Supplied materials and ownership: raw materials from the principal, ownership during processing, yield, by-products.
- Investments: who finances equipment or moulds, amortisation, compensation on early termination.
- Approval and hygiene: duty to maintain the approval, notification of official measures.
- Quality and audit: quality assurance agreement, releases, retained samples, audit rights.
- Traceability and recall: batch formation, response times, crisis contacts, costs.
- Price: processing fee or unit price, price adjustment for energy and labour costs.
- Exclusivity: non-compete obligations within the limits of competition law.
- Liability, insurance, force majeure: areas of responsibility, caps, animal diseases and business interruptions.
- Term and termination: minimum term, termination, run-off phase, handover of documents.
Supplied materials, ownership and yield
If the principal supplies the raw materials, such as animals for slaughter, milk or meat cuts, the question of ownership is an underestimated issue. Under Section 950 BGB, whoever produces a new item by processing acquires ownership of it, unless the value of the processing is considerably less than the value of the material. According to the prevailing view, the producer within the meaning of this provision is the person in whose name and economic interest production takes place. A clear processing clause creates certainty, including in the event of the manufacturer’s insolvency.
„The supplied raw materials are processed for the principal. The principal remains the owner of the raw materials and becomes the owner of the intermediate and finished products. The manufacturer shall store them free of charge with the care of a prudent businessperson and mark them separately.“
Yield is just as important. The contract should specify what quantity of finished goods is to be expected from a given quantity of raw material, which deviations are tolerated and who is entitled to by-products. In meat processing, there are also animal by-products, which must be disposed of or used in accordance with Regulation (EC) No 1069/2009. Many contracts do not regulate the costs of this.
Food law specifics
Approval and identification mark
An establishment that manufactures food of animal origin for which Annex III to Regulation (EC) No 853/2004 lays down requirements needs an approval from the competent authority. The product bears that establishment’s identification mark. The contract should oblige the manufacturer to maintain the approval and to inform the principal immediately if the authority imposes conditions, finds deficiencies or a suspension of the approval is imminent. A production stoppage due to official measures is a considerable supply risk for the principal.
Labelling
Under Article 8(1) of the Food Information to Consumers Regulation (FIC, in German LMIV), the operator responsible for labelling is the business under whose name the product is marketed. If products are sold under the principal’s brand, responsibility lies with the principal. The manufacturer, however, owes the correct implementation of the recipe and must report if the actual composition no longer matches the labelling under the FIC. For meat products, the Leitsätze (guidelines) of the German Food Code (Deutsches Lebensmittelbuch) must also be observed, as they reflect consumer expectations regarding name and composition.
Traceability, recall and audit
For food of animal origin, Implementing Regulation (EU) No 931/2011 specifies the traceability information that must be passed on between businesses, including quantity, batch or consignment number and date of dispatch. The contract should organise the transmission of this data. For recalls under Article 19 of Regulation (EC) No 178/2002, it should be clear who informs the authority and how communication is coordinated. In long-term production agreements, the principal’s audit right is regularly drawn more widely than in simple supply agreements and often includes unannounced visits.
Investments, exclusivity and term
If the manufacturer invests in equipment that it uses only for the principal, it will require a minimum term or a purchase guarantee. Alternatively, the principal can finance the investment and become the owner of the equipment. Maintenance, insurance and handover at the end of the contract must then be regulated. On early termination through no fault of the manufacturer, compensation for the part not yet amortised is customary.
Non-compete obligations on the manufacturer are exempted under the Vertical Block Exemption Regulation (EU) 2022/720 if the market share thresholds are met and the obligation does not exceed five years. In subcontracting situations, the Commission Notice on subcontracting agreements can also be relied on. Whether exclusivity holds up under competition law should be checked before the contract is concluded.
For the end of the contract, a run-off phase is advisable in which the manufacturer continues to supply until a successor is producing. In addition, the manufacturer should be obliged to hand over specifications, supplier data and process parameters to the extent that the principal is entitled to them.
Pricing
Where the raw materials are supplied, a processing fee per kilogram or per unit is usually agreed; otherwise a unit price including raw materials. For long terms, a cost element clause that records energy, wages and packaging separately and links them to traceable indices is a good option. An annual date on which the parties review the calculation together also makes sense. This keeps the parties talking even when costs jump unexpectedly, without one side having to terminate the contract.
Liability, insurance and typical mistakes
Liability should be allocated by area of responsibility: manufacturing and hygiene errors to the manufacturer, recipe and labelling errors to the principal, defects in supplied raw materials to whoever supplied them. For the manufacturer, a rule that it is not liable for the consequences of official measures for which it is not responsible is also important. Both sides should provide proof of product liability and product recall insurance. For the principal, contingent business interruption insurance covering the supplier can also make sense.
Typical mistakes from our practice:
- Capacity reservation without consequences: the manufacturer commits capacity, but other customers are given priority when capacity is tight.
- No provision on animal diseases: an outbreak of African swine fever or avian influenza can interrupt supply chains. Without a clear force majeure rule, it is unclear who bears the risk.
- Prices without an adjustment mechanism for energy and labour costs, which over long terms lead to renegotiations under pressure.
- No provision on ownership of supplied goods, which leads to disputes over the right to separate them from the estate in the manufacturer’s insolvency.
How we support you
We draft production agreements for brand manufacturers, retailers and processors, in German and English, examine competition law questions of exclusivity and term, and regulate supplied materials, ownership and investment protection. If the authorities take measures against the manufacturing establishment, we support you in the proceedings before the food control authorities. For basic questions of contract production, read our page on contract manufacturing and private label. You can describe your project to us via the online enquiry.
Four examples from our practice
Insolvency of the meat processor
Situation: A brand manufacturer had ham produced by a processor from legs it supplied itself. The processor became insolvent. The insolvency administrator claimed the goods in the warehouse as part of the insolvency estate.
Solution: On the basis of the processing clause and the separate storage, we asserted the right to separation from the estate. For the future, we anchored the marking of supplied goods and regular stock reports in the contract.
Suspension of the approval
Situation: At a cheese manufacturer, the authority found serious hygiene deficiencies and ordered measures. The principal only learned of this when deliveries stopped arriving.
Solution: We examined which claims followed from the breach of the duty to notify and quickly brought in a replacement manufacturer under contract. The new production agreement contains a duty to report official measures within 24 hours.
Investment in a filling line
Situation: A manufacturer of ready-made soups invested in a line for a single customer. After two years, the customer wanted to terminate the contract with ordinary notice.
Solution: We calculated and enforced the agreed investment compensation. It helped that the contract contained an amortisation schedule as an annex.
Avian influenza and supply failure
Situation: After an outbreak of avian influenza in the region, a cutting plant could not supply the agreed quantities. The principal claimed damages for the cost of alternative sourcing.
Solution: We interpreted the force majeure clause and documented the official restrictions. The parties agreed on a temporary reduction in quantities without damages.
Frequently asked questions
How does a production agreement differ from a contract manufacturing agreement?
The terms are not used consistently. We speak of a production agreement when a long-term commitment of capacity with investments or supplied materials is the main feature. The contract manufacturing agreement (Lohnherstellervertrag) concerns order-based manufacture to the principal's recipe.
Does the principal itself need an approval under Regulation 853/2004?
Not if it only sells the goods under its name and does not manufacture or repack them itself. It remains a food business operator, however, and generally has to be registered as such.
How long may an exclusivity commitment run?
Under the Vertical Block Exemption Regulation, non-compete obligations of up to five years are exempted if neither party's market share exceeds 30 per cent. Longer commitments are not automatically prohibited, but require an individual assessment.
Who bears the disposal costs for animal by-products?
The law sets out the duties under Regulation (EC) No 1069/2009, not the allocation of costs between the contracting parties. Without a provision, disputes arise easily, so the contract should assign the costs expressly.